|
Thursday, April 22,
2004
Battle Creek still closed
Tonnage still an issue between DEQ and NWS
By
Jamie Turner Staff Writer
The gates to Battle Creek Landfill remain closed despite
a Richmond court order earlier this month that called for the disposal
facility to reopen as early as April 19.
But this week the only traffic entering and exiting
Battle Creek are county employees and those working for landfill operators
National Waste Services (NWS) of Virginia.
On April 6 Richmond City Circuit Court Judge Theodore J.
Markow granted a temporary restraining order on NWS’ behalf. The court
ruling called for the landfill to reopen because the company was suffering
financially after the landfill was closed by the state Department of
Environmental Quality March 10.
The DEQ pulled the landfill’s operating permit and the
facility was shut down.
Markow said the facility should reopen once DEQ and NWS
reached an agreement on how to safely operate the landfill. Markow’s
ruling called for an agreement by April 19. But as of early this week,
there was no compromise between DEQ and NWS.
The big hang up in the negotiations revolves around
tonnage limits. It is the same contentious issue that was cited when the
state began permit revocation proceedings eight months ago.
DEQ agrees to reopen Battle Creek if NWS accepts only
250 tons of waste per day, a limit the state says is spelled out in the
landfill’s operating permit. The state is also requesting that NWS invest
further in financial assurances.
NWS is opposed to both conditions.
In the meantime, Page County filed a motion to intervene
in the negotiations. As the permit holder, Page wants to be included in
the ruling.
Since DEQ and NWS could not reach an agreement by April
19, both parties submitted separate lists of conditions and assurances for
Battle Creek to renew operations. Now Markow must choose which set of
rules NWS will follow when the landfill reopens, which could happen within
the next two weeks.
Tonnage
DEQ officials came up with a list of operating rules for
NWS. NWS has agreed to most of them, except a tonnage limit.
The state is calling for a 250-ton limit on the intake
of waste at Battle Creek, a figure they say is included in Page County’s
current operating permit.
NWS disagrees.
“In order for the landfill to break even financially it
must accept, on average, nearly 1,200 tons of waste per day,” states an
April 16 letter from NWS attorney Patrick Cavanaugh to Markow. “The state
has suggested that the landfill should be limited to accepting but a
fraction of that amount, namely 250 tons per day. The amount proposed by
the state is a restriction it has fabricated, and it is one that NWS has
sought to contest in a declaratory judgment action that is pending with
this court.”
One month prior to the landfill closure, NWS was
averaging about 1,500 tons of waste per day. The high amounts of trash
hauled into Battle Creek was one of DEQ’s main argument for shutting down
the facility.
DEQ officials did not want to comment on the debate with
NWS over tonnage.
NWS said they cannot viably operate Battle Creek by
dumping just 250 tons per day.
Financing
DEQ is also requesting NWS to add an additional $2
million onto its existing $4.3 million closure and post-closure assurance
bond.
The state is asking for another $2 million performance
bond as well. This is in addition to the current $1 million
performance bond the company with Page County.
“Aside from the fact that DEQ itself deemed NWS’s $4.3
million bonding sufficient less than two months ago, and no changes have
been made to the site, there is no engineering evidence that DEQ could now
offer to support its position,” NWS’s Cavanaugh said. “The notion that DEQ
should now be allowed to impose an additional $2 million in closure and
post-closure financial protections, or another $2 million in performance
bonds, cannot be justified and should be rejected.”
The request for additional assurance bonds from NWS
comes after the Delaware-based company filed for Chapter 11 bankruptcy
this April.
NWS says its bankruptcy filing was a way to protect its
business from the state. And in recent court documents, NWS said it made a
$3.8 million profit in 2003.
Intervention
As the negotiation plays out between DEQ and NWS, Page
County’s landfill attorney James E. Cornwell Jr. recently filed a motion
to intervene in the case. Cornwell said county officials want to be
included in the Richmond court proceedings.
“If the judge allows it, we will be making comments on
DEQ’s and NWS’s orders,” Cornwell said.
Both the landfill permit and property Battle Creek sits
on belong to Page County. Cornwell said the county should be privy to any
decisions made involving Battle Creek.
Cornwell met with NWS attorneys April 19 to discuss the
company’s future plans at Battle Creek after the facility reopens.
For its part, NWS aims to use the negotiations to
rebuild its partnership with Page County and the state.
“Our goal is to try if possible to build a new
relationship with the county and DEQ,” said Scott Andrews, of
Winston-Partners, the McLean-based company with controlling interest in
NWS. “We are trying to come up with a resolution that works with
everybody. And I believe there have been signs of progress in the past 10
days.”
Andrews said NWS has been working with DEQ and Page
County for the past two weeks ironing out differences.
While NWS is hoping to mend the fence, Andrews said
there final goal is to reopen Battle Creek.
“We believe it is in the best interest for the citizens
of Page County to have the landfill reopen in the near future,” he
said.
In the meantime, Page County landfill inspectors
reported Tuesday that Battle Creek’s leachate system was leaking. The leak
was reported to the state.
We can be reached at pagenews@shentel.net. |